Channel on Jalan Dharma Wanita I Rawa Buaya Widened
access_time August 29 2024 09:27 AM remove_red_eye 231
Reported by TP Moan Simanjuntak | Translated by Nugroho Adibrata
Reported by TP Moan Simanjuntak | Translated by Nugroho Adibrata
The West Jakarta Water Resources Sub-agency (SDA) is widening the water channel on Jalan Dharma Wanita I, RT 11/01, Rawa Buaya Urban Village, Cengkareng Sub-district. Some parts of the channel sheet piles are also repaired.
Hopefully, we can be free of flooding
West Jakarta SDA Sub-agency Head, Purwanti said the total length of the widened and repaired channel was 350 meters using 60x60 and 80x80 centimeter U-ditches which were then covered with concrete casting.
"The channel was there before but it was small. Then the sheet pile was also damaged so we repaired it," she expressed, Thursday (8/29).
September, Channel Widening at Gg Ribi CompletedShe explained it has been ongoing since August 7, 2024, and is targeted for completion on December 4, 2024.
"Hopefully, the widening is carried to smoothen water flow into the Mookevart River, thus flooding can be minimized," she explained.
The work received appreciation from RW 01 Chairman, Rawa Buaya Urban Village, Sahri.
"Hopefully, we can be free of flooding," he hoped.